- Drawing revision letters for RFQ 5125, 5127 and 5129Ingrid Solheim. None of the three can enter engineering review without them.Due Oct 6
- Signed decision on quote Q-9235Ingrid Solheim. Accept, decline or a written question.Due Oct 7
- Decisions on the bore tolerance, flange flatness and port thread, on revision DIngrid Solheim. A marked-up drawing or a written answer for RFQ 5102, 5111 and 5124.Due Oct 8
- Signed acceptance or decline of the order 2287 changeIngrid Solheim. Nothing is released before it arrives.Due Oct 9
- Housing drawings, revision DReceived by email on Sep 24 and logged as the accepted revision for quoting.Received