Orders at a glance
Status as of Sep 28, 2026 2 confirmed exceptions 1 order needs review: 9 days apart
The committed date for each of the 11 open Tarrow orders, taken from the last authorized commitment, with the two confirmed casting delays disclosed and one order held for a decision because its system date and its committed date differ by 9 days. Prepared by the Keelson customer service lead from approved sources for the Tarrow planner and buyer, including Ingrid Solheim, director of purchasing at Tarrow Pump Systems. Rosalind Chau, vice president of engineering at Keelson Precision Manufacturing, decides which date is supportable. Benedict Oyelaran, commercial operations manager, publishes the status. The next status is published on Oct 12.
Orders on their last authorized commitment
Eight of the 11 open orders are on their last authorized commitment. Two carry a confirmed exception and one needs a supportable date. The count below is the one the Tarrow planner sees first.
Open orders on their last authorized commitment, 8 of 11
Open orders and their dates
Dates are in days from Sep 28. Each row shows the last authorized commitment, the current production date and a short note. Eight rows have the same number in both columns.
Order 2287 is one of the eight on commitment. Its committed date is Nov 7 at 400 units, and the quantity change from 400 to 650 is at impact review. If Tarrow accepts the change, the date for that order moves to Nov 28, and that is a separate decision recorded on the order change impact review.
Committed date and current date
Each pair of points is one order that is not on its last authorized commitment. The gap between the points is how far the current production date is from the commitment. Two gaps are 14 days and one is 9 days.
| Order | Part | Quantity | Order value | Committed | Current | Gap | State |
|---|---|---|---|---|---|---|---|
| Tarrow order 2284 | HSG-410-D pump housings | 90 | $58,950 | Oct 26 | Nov 9 | 14 days | Confirmed exception |
| Tarrow order 2291 | HSG-512-D pump housings | 75 | $67,875 | Nov 2 | Nov 16 | 14 days | Confirmed exception |
| Tarrow order 2295 | IMP-310-B impellers | 250 | $31,500 | Nov 7 | Nov 16 | 9 days | Needs review |
Where each date comes from
A date is published only if it comes from an approved source. The production system date is shown beside the commitment for comparison and is never published as a commitment on its own.
- Last authorized commitment
- The date Rosalind Chau authorized and Keelson gave Tarrow in writing, held on the order with its ERP reference.
- Approved order milestones
- Milestones such as material received, machining complete and ready to ship, each confirmed by the plant before it is published.
- Confirmed exceptions
- A delay confirmed with the supplier and signed off by Rosalind Chau, disclosed with its cause and the date recovery is expected.
- Production system date
- The current date in the production system. It can move after a machine reassignment, and it does not change the commitment until someone decides it should.
- Source refresh
- Sep 28, 2026. The next refresh is Oct 8, before approval on Oct 9.
- Customer decision
- Tarrow decides delivery date changes. Keelson does not move a committed date on its own.
"A date that moved in the system is not a date we have promised. The supportable date is the one I can stand behind in front of Tarrow."
Rosalind Chau, Vice president of engineering, Keelson Precision Manufacturing
Review steps
The status goes through four steps before each publication. The marks show the Oct 12 cycle as of Oct 1.
- Source refreshed Sep 28
- Exception review, order 2295 open
- Status approved, Oct 9
- Published, Oct 12
- Decide the supportable date for order 2295. Owner: Rosalind Chau, Oct 9open
- Confirm the casting recovery date with the supplier for orders 2284 and 2291. Owner: Benedict Oyelaran, Oct 9open
- Acknowledge the two delayed dates or ask for a different date. Owner: Ingrid Solheim, Oct 9open
- Publish the next status with the two exceptions disclosed and the casting recovery date. Owner: Benedict Oyelaran, Oct 12open
- Disclose the two confirmed exceptions in the Sep 28 status. Owner: Benedict Oyelaran, donedone
Exception sign-off
- Rosalind ChauVice president of engineering, Keelson Precision Manufacturing, signs the exceptions and the supportable date
- Benedict OyelaranCommercial operations manager, Keelson Precision Manufacturing, publishes the status
- Ingrid SolheimDirector of purchasing, Tarrow Pump Systems, acknowledges the dates