Housing and impeller program with Keelson Precision Manufacturing
Four decisions are yours between Oct 6 and Oct 9.
Three RFQs wait for a drawing revision letter, the housing family quote needs your decision, the bore tolerance waits on revision D, and order 2287 would grow from 400 to 650 units and add 3 weeks. Keelson recommends and you decide. Nothing is released before you answer.

Decision status
DecisionsAll four are Tarrow's to decide, in date order. Today is Thursday, Oct 1.
- Tue Oct 6Revision letters for three RFQsRFQ 5125, 5127 and 5129. RFQ 5125 has waited 8 days.Waiting on you
- Wed Oct 7Housing family quote Q-9235Record your decision on the issued quote.Waiting on you
- Thu Oct 8Revision D answersBore tolerance, flange flatness and port thread. The bore question is 9 days old.Waiting on you
- Fri Oct 9Order 2287 change400 to 650 impellers. Adds 3 weeks, from Nov 7 to Nov 28.Waiting on you
Decision sheet
- 6Tue Oct
Send the drawing revision letters
Which drawing revision applies to RFQ 5125, 5127 and 5129. Each RFQ is missing only that fact.
- Keelson recommends
- Send all three together. Benedict releases complete RFQs to engineering review on Oct 7.
- If it waits
- The RFQs cannot enter engineering review, so no quote starts and its 30 day validity cannot begin.
- 7Wed Oct
Record your decision on quote Q-9235
Accept, decline or ask a question on the quote for the new housing family. Rosalind Chau approved its price and capacity.
- Keelson recommends
- Read the issued quote and its valid-until date, and ask Benedict anything unclear before you decide.
- If it waits
- Nothing is ordered from the quote until you answer. It stays valid for 30 days from issue.
- 8Thu Oct
Decide the three questions on revision D
Bore tolerance on RFQ 5102, flange flatness on RFQ 5111 and the port thread class on RFQ 5124.
- Keelson recommends
- Decide the bore tolerance first. Keelson records your decision and does not choose between two readings of a drawing.
- If it waits
- The RFQ 5102 quote cannot take a bore tolerance, so the housing quote is not built.
- 9Fri Oct
Accept or decline the order 2287 change
Raise order 2287 from 400 to 650 impellers, part IMP-220-B. The revised offer adds $29,500 and 3 weeks.
- Keelson recommends
- Accept only if a Nov 28 delivery works for your builds. If Nov 7 matters more, decline and the order stays at 400.
- If it waits
- The order stays at 400 units on Nov 7. No material is released and no rescheduling starts.
Also due Oct 9: acknowledge the two casting delays on orders 2284 and 2291, or ask for a different date. See Delivery.
The record behind the four decisions
Evidence and resultsCounts from the RFQ and quote register and the order and change register, through Sep 28.
- RFQs complete on the first pass
- 9 of 14
- Questions incorporated
- 15 of 22
- Quotes from approved inputs, first pass
- 6 of 8
- Open orders on their authorized date
- 8 of 11
3 still wait for a revision letter
3 wait for your decision
September, $412,000 issued
2 casting delays disclosed
Who decides what
- Ingrid SolheimDirector of purchasing, Tarrow. Decides the four items on the sheetDecides
- Rosalind ChauVice president of engineering, Keelson. Decides feasibility, price, capacity and supportable dates
- Benedict OyelaranCommercial operations manager, Keelson. Owns the RFQ, revision, change and delivery status queues
Recent activity
Files- BOBenedict issued quote Q-9235New housing family, valid 30 days from issue. Your decision is due Oct 7.
- BOBenedict published the Sep 28 statusEight of 11 orders on their last authorized date, two casting delays disclosed.
- BOBenedict returned three RFQs to youEach names the missing drawing revision letter. Reply owed Oct 6.
- RCRosalind accepted revision D for quotingThe three open revision C questions were asked again on revision D.
- ISRevision D reached Keelson by emailSent to a Keelson salesperson while engineering was quoting revision C.
Your contact: Benedict Oyelaran
RFQs, revisions, changes and delivery status. Questions about a decision go here before you answer, and the answer stays with the record.
- RCRosalind ChauVice president of engineering, Keelson
- ISIngrid SolheimDirector of purchasing, Tarrow, decides